Construction Update: August 3, 2020

A traffic improvement project will take place Aug. 3 through Sept. 3 on Briarcliff Road.

Thank you for your patience as we continue construction on the North Druid Hills campus. Below you will find construction updates and traffic impacts related to this development.

Construction on Briarcliff Road to Begin Monday, August 3

Construction on a traffic improvement project at the Children’s driveway at Briarcliff will begin next week. We have worked closely with DeKalb County to develop a detailed traffic control plan to minimize the traffic impact. All work is expected to be completed by Thursday, September 3, weather permitting. The work is segmented into two phases, as shown below:

Phase 1: August 3-9

No impact on Briarcliff Road or the sidewalk is anticipated. Barriers will separate all work from the current sidewalk.

construction traffic update

Phase 2: August 10-September 3

The second phase will require a lane shift that will reduce traffic on Briarcliff Road to two lanes. Two-way traffic will be maintained, and traffic facilitation measures will be in place at all times.

Briarcliff road traffic improvement project update